ML Harris — Infrastructure Advisory
Site Calculator

This tool is available to approved partners and clients only. Access is provided via your personalised link.

See The Tool
I already have a token
Site Calculator
Turn Land Into Live Capacity.
Planning consent and environmental clearance assumed. Calculates buildable IT capacity from land area and grid connection. Minimum viable site: 10 MW IT load — sites below this threshold are flagged as sub-commercial.
01 — Site Geometry
Total Site Area iTotal land parcel. Planning consent and environmental clearance are assumed. Switch units for UK (acres), EU (hectares), or raw m².
Approved Land Coverage (%) iPlanning-consented percentage of the site that can carry built structures. Typical data centre range: 25–45% including M&E plant yards.
Max Permitted Building Height iPlanning-consented maximum structural height. Taller shells unlock additional storeys, which multiply gross floor area and drive up supporting-infrastructure requirements (plant yard, cooling, substation). Typical data hall floor-to-floor: 7m. Ground floor with plant: 8m.
Data Hall Efficiency (%) iPercentage of gross floor area that becomes usable server floor. Plant rooms, corridors, loading bays, and offices account for the rest. Industry norm: 55–65%.
02 — Grid Connection
Grid Connection (MVA) iApparent power from the grid operator. A 10% power factor deduction is applied. 100 MVA yields approximately 90 MW of usable real power.
Independent Grid Feeds iTier III and IV require two independent feeds from separate substations. A single feed places full backup dependency on on-site generation.
Generator Unit Size (MW) iSize of each standby generator unit. Modern data-centre standard is 2.5 MW (CAT 3516E / MTU 20V class). Larger units reduce count but need more yard space. The tool auto-computes the number of units required for the selected Tier's redundancy scheme (N, N+1, or 2N).
03 — Build Specification
Target PUE iPower Usage Effectiveness = total facility draw ÷ IT load. Google fleet: 1.09. Modern design target: 1.30. Industry average: 1.56. EU Energy Efficiency Directive 2023 caps new-build DCs above 500 kW at PUE ≤ 1.5 by 2030. Germany's Energiedienstleistungsgesetz requires PUE ≤ 1.3 for new sites from 2026.
Cooling Method iAir cooling suits ≤20kW/rack. Hybrid combines free-cooling and mechanical. Liquid cooling is required for AI and HPC workloads above 20kW/rack.
Uptime Tier / EN 50600 Class iUptime Institute Tier and the CENELEC EN 50600-2-1 Availability Class are harmonised. Tier II ≈ Class 2 (N, redundant components). Tier III ≈ Class 3 (N+1, concurrent maintainability). Tier IV ≈ Class 4 (2N, fully fault-tolerant). EN 50600 is the European benchmark; most EU clients require Class 3 minimum for commercial facilities.
Target Rack Density (kW / rack) iStandard enterprise IT: 8kW. AI inference: 30–60kW. Training clusters: 100kW+. Above 20kW triggers liquid cooling requirement.
Rack Pitch (m² / rack) iFloor area per rack including hot/cold aisles and service clearance. 2.0 m² is dense hyperscale with cold-aisle containment. 2.5 m² is the Uptime Institute industry reference. 3.0 m² applies to wider-aisle enterprise or Tier IV with service corridors. 4.0 m² covers legacy and co-lo deployments.
A — Overall Viability
B — Power Chain
C — Space and Racks
D — On-Site Generation
E — Land Use Breakdown
Building footprint (consented)
M&E plant yard (estimated)
Cooling plant area (estimated)
Access roads and parking
Open land, buffers, green space
Supporting infrastructure sized from facility draw — plant yard 500 m²/MW, cooling 100/175/275 m²/MW (Air/Hybrid/Liquid), substation 80 m²/MW, roads 300 m²/MW + 2,000 m² base. Industry benchmark: 30–40% of a campus is actively developed. If the support bars exceed the consented footprint, the tool flags the site as not feasible.
F — Land Intensity & Sizing
Reverse sizing — what land do I need?
MW IT
Minimum developable land to deliver the target IT load at current coverage, efficiency, density and pitch. Does not account for planning buffers beyond those already captured in "Approved Land Coverage".
G — Not Modelled
Grid connection cost and lead time (18–24 months for large power transformers)
Fibre carrier diversity and proximity to nearest IXP (AMS-IX, DE-CIX, LINX, INEX)
Water availability and Water Usage Effectiveness (WUE) — up to 19M L/day for large evaporative systems
Planning fees, S106 / PLU / BauNVO / Bestemmingsplan obligations and infrastructure contributions
Construction cost per MW (UK / EU typically £8–14M or €10–16M/MW fully fitted)
EU Energy Efficiency Directive reporting (Art. 12), CSRD sustainability disclosure, and EU Taxonomy alignment
F-Gas Regulation (EU 517/2014) restrictions on refrigerants — affects chiller selection
Renewable Energy Directive III (RED III) and EU ETS carbon pricing exposure
Full EN 50600 series compliance audit — availability, security, energy efficiency

Indicative outputs only — verify with qualified engineers before committing capital. Use is governed by the Terms of Use and Cookies Statement.