Building footprint (consented)
M&E plant yard (estimated)
Cooling plant area (estimated)
Open land, buffers, green space
Supporting infrastructure sized from facility draw — plant yard 500 m²/MW, cooling 100/175/275 m²/MW (Air/Hybrid/Liquid), substation 80 m²/MW, roads 300 m²/MW + 2,000 m² base. Industry benchmark: 30–40% of a campus is actively developed. If the support bars exceed the consented footprint, the tool flags the site as not feasible.
Reverse sizing — what land do I need?
Minimum developable land to deliver the target IT load at current coverage, efficiency, density and pitch. Does not account for planning buffers beyond those already captured in "Approved Land Coverage".
—Grid connection cost and lead time (18–24 months for large power transformers)
—Fibre carrier diversity and proximity to nearest IXP (AMS-IX, DE-CIX, LINX, INEX)
—Water availability and Water Usage Effectiveness (WUE) — up to 19M L/day for large evaporative systems
—Planning fees, S106 / PLU / BauNVO / Bestemmingsplan obligations and infrastructure contributions
—Construction cost per MW (UK / EU typically £8–14M or €10–16M/MW fully fitted)
—EU Energy Efficiency Directive reporting (Art. 12), CSRD sustainability disclosure, and EU Taxonomy alignment
—F-Gas Regulation (EU 517/2014) restrictions on refrigerants — affects chiller selection
—Renewable Energy Directive III (RED III) and EU ETS carbon pricing exposure
—Full EN 50600 series compliance audit — availability, security, energy efficiency